Annex No. 3 to the EPC contract has been signed
31.01.2022
Annex No. 3 to the EPC contract has been signed

On 28th January 2022 the Management Board of Grupa Azoty Polyolefins and the General Contractor - HyundaI Engineering signed Annex No. 3 to the EPC contract.

Annex no. 3 approves:

  • increasing the contractor's remuneration by EUR 72.48 million,
  • extension of the project implementation schedule by 6 months
  • changes in the technical area.

In accordance with the Management Board resolution, the signing of the annex was preceded by obtaining the necessary approvals from all corporate bodies.